Located in the heart of Springfield, the Kalina Sales Hub is a standalone, off-grid sales office, which is the first of its kind in Australia. Stockland required the sales hub to completely self-sufficient as a grid connection would not be available for another 6 months.
The project was completed within three weeks of engagement, including both design and construct.
The Infrastructure Services team installed 6kW of photovoltaic (PV) cells with nearly 10kWh of battery storage. This allows the office to run air conditioning, refrigeration, computers, light, power, security, etc and operate as a usual office.
At an equivalent cost to a grid connection, the self-sufficient nature of the sales hub allows it to be relocated as needed.
The project delivery included the complete design and construct for the solar installation.
The team installed:
Brisbane Head Office